Upgrade duration requirement
[escalator.git] / docs / requirements / 104-Requirements.rst
1 ============
2 Requirements
3 ============
4
5 Upgrade duration
6 ================
7
8 Being a telecom service system, OPNFV shall target at carrier grade availability,
9 which allows only about 5 minutes of outage in a year. Base on this basic input
10 and discussions on the current solutions, The following requirements are defined
11 from the perspective of time constraints:
12
13 - OPNFV platform must be deployed with HA to allow live upgrade possible. Considering of
14   the scale, complexity, and life cycle of OPNFV system, allocating less than
15   5 minutes out of a year for upgrade is in-realistic. Therefore OPNFV should
16   be deployed with HA, allowing part of system being upgraded, while its
17   redundant parts continue to serve End-User. This hopefully relieves the time
18   constraint on upgrade operation to achievable level.
19
20 - VNF service interruption for each switching should be sub-second range. In
21   HA system, switching from an in-service system/component to the redundant
22   ones normally cause service interruption. From example live-migrating a
23   virtual machine from one hypervisor to another typically take the virtual
24   machine out of service for about 500ms. Summing up all these interruptions in
25   a year shall be less than 5 minutes in order to fulfill the five-nines carrier
26   grade availability. In addition, when interruption goes over a second, End-User
27   experience is likely impacted. This document therefore recommends service
28   switching should be less than a second.
29
30 - VIM interruption shall not result in NFVI interruption. VIM in general has more
31   logic built-in, therefore more complicated, and likely less reliable than NFVI.
32   To minimize the impact from VIM to NFVI, unless VIM explicitly order NFVI stop
33   functioning, NFVI shall continue working as it should.
34
35 - Total upgrade duration should be less than 2 hours. Even time constraint is
36   relieved with HA design, the total time for upgrade operation is recommended
37   to limit in 2 hours. The reason is that upgrade might interfere End-User
38   unexpectedly, shorter maintenance window is less possible risk. In this
39   document, upgrade duration is started at the moment that End-User services
40   are possibly impacted to the moment that upgrade is concluded with either
41   commit or rollback. Regarding on the scale and complexity of OPNFV system,
42   this requirements looks challenging, however OPNFV implementations should
43   target this with introducing novel designs and solutions.
44
45 Pre-upgrading Environment
46 =========================
47
48 System is running normally. If there are any faults before the upgrade,
49 it is difficult to distinguish between upgrade introduced and the environment
50 itself.
51
52 The environment should have the redundant resources. Because the upgrade
53 process is based on the business migration, in the absence of resource
54 redundancy,it is impossible to realize the business migration, as well as to
55 achieve a smooth upgrade.
56
57 Resource redundancy in two levels:
58
59 NFVI level: This level is mainly the compute nodes resource redundancy.
60 During the upgrade, the virtual machine on business can be migrated to another
61 free compute node.
62
63 VNF level: This level depends on HA mechanism in VNF, such as:
64 active-standby, load balance. In this case, as long as business of the target
65 node on VMs is migrated to other free nodes, the migration of VM might not be
66 necessary.
67
68 The way of redundancy to be used is subject to the specific environment.
69 Generally speaking, During the upgrade, the VNF's service level availability
70 mechanism should be used in higher priority than the NFVI's. This will help
71 us to reduce the service outage.
72
73 Release version of software components
74 ======================================
75
76 This is primarily a compatibility requirement. You can refer to Linux/Python
77 Compatible Semantic Versioning 3.0.0:
78
79 Given a version number MAJOR.MINOR.PATCH, increment the:
80
81 MAJOR version when you make incompatible API changes,
82
83 MINOR version when you add functionality in a backwards-compatible manner,
84
85 PATCH version when you make backwards-compatible bug fixes.
86
87 Some internal interfaces of OpenStack will be used by Escalator indirectly,
88 such as VM migration related interface between VIM and NFVI. So it is required
89 to be backward compatible on these interfaces. Refer to "Interface" chapter
90 for details.
91
92 Work Flows
93 ==========
94
95 Describes the different types of requirements.  To have a table to label the source of
96 the requirements, e.g. Doctor, Multi-site, etc.
97
98 Basic Actions
99 =============
100
101 This section describes the basic functions may required by Escalator.
102
103 Preparation (offline)
104 ^^^^^^^^^^^^^^^^^^^^^
105
106 This is the design phase when the upgrade plan (or upgrade campaign) is
107 being designed so that it can be executed automatically with minimal
108 service outage. It may include the following work:
109
110 1. Check the dependencies of the software modules and their impact,
111    backward compatibilities to figure out the appropriate upgrade method
112    and ordering.
113 2. Find out if a rolling upgrade could be planned with several rolling
114    steps to avoid any service outage due to the upgrade some
115    parts/services at the same time.
116 3. Collect the proper version files and check the integration for
117    upgrading.
118 4. The preparation step should produce an output (i.e. upgrade
119    campaign/plan), which is executable automatically in an NFV Framework
120    and which can be validated before execution.
121
122    -  The upgrade campaign should not be referring to scalable entities
123       directly, but allow for adaptation to the system configuration and
124       state at any given moment.
125    -  The upgrade campaign should describe the ordering of the upgrade
126       of different entities so that dependencies, redundancies can be
127       maintained during the upgrade execution
128    -  The upgrade campaign should provide information about the
129       applicable recovery procedures and their ordering.
130    -  The upgrade campaign should consider information about the
131       verification/testing procedures to be performed during the upgrade
132       so that upgrade failures can be detected as soon as possible and
133       the appropriate recovery procedure can be identified and applied.
134    -  The upgrade campaign should provide information on the expected
135       execution time so that hanging execution can be identified
136    -  The upgrade campaign should indicate any point in the upgrade when
137       coordination with the users (VNFs) is required.
138
139 .. <hujie> Depends on the attributes of the object being upgraded, the
140   upgrade plan may be slitted into step(s) and/or sub-plan(s), and even
141   more small sub-plans in design phase. The plan(s) or sub-plan(s) my
142   include step(s) or sub-plan(s).
143
144 Validation the upgrade plan / Checking the pre-requisites of System( offline / online)
145 ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
146
147 The upgrade plan should be validated before the execution by testing
148 it in a test environment which is similar to the product environment.
149
150 .. <MT> However it could also mean that we can identify some properties
151   that it should satisfy e.g. what operations can or cannot be executed
152   simultaneously like never take out two VMs of the same VNF.
153
154 .. <MT> Another question is if it requires that the system is in a particular
155   state when the upgrade is applied. I.e. if there's certain amount of
156   redundancy in the system, migration is enabled for VMs, when the NFVI
157   is upgraded the VIM is healthy, when the VIM is upgraded the NFVI is
158   healthy, etc.
159
160 .. <MT> I'm not sure what online validation means: Is it the validation of the
161   upgrade plan/campaign or the validation of the system that it is in a
162   state that the upgrade can be performed without too much risk?==
163
164 Before the upgrade plan being executed, the system healthy of the
165 online product environment should be checked and confirmed to satisfy
166 the requirements which were described in the upgrade plan. The
167 sysinfo, e.g. which included system alarms, performance statistics and
168 diagnostic logs, will be collected and analogized. It is required to
169 resolve all of the system faults or exclude the unhealthy part before
170 executing the upgrade plan.
171
172
173 Backup/Snapshot (online)
174 ^^^^^^^^^^^^^^^^^^^^^^^^
175
176 For avoid loss of data when a unsuccessful upgrade was encountered, the
177 data should be back-upped and the system state snapshot should be taken
178 before the execution of upgrade plan. This would be considered in the
179 upgrade plan.
180
181 Several backups/Snapshots may be generated and stored before the single
182 steps of changes. The following data/files are required to be
183 considered:
184
185 1. running version files for each node.
186 2. system components' configuration file and database.
187 3. image and storage, if it is necessary.
188
189 .. <MT> Does 3 imply VNF image and storage? I.e. VNF state and data?==
190
191 .. <hujie> The following text is derived from previous "4. Negotiate
192   with the VNF if it's ready for the upgrade"
193
194 Although the upper layer, which include VNFs and VNFMs, is out of the
195 scope of Escalator, but it is still recommended to let it ready for a
196 smooth system upgrade. The escalator could not guarantee the safe of
197 VNFs. The upper layer should have some safe guard mechanism in design,
198 and ready for avoiding failure in system upgrade.
199
200 Execution (online)
201 ^^^^^^^^^^^^^^^^^^
202
203 The execution of upgrade plan should be a dynamical procedure which is
204   controlled by Escalator.
205
206 .. <hujie> Revised text to be general.==
207
208 1. It is required to supporting execution ether in sequence or in
209    parallel.
210 2. It is required to check the result of the execution and take the
211    action according the situation and the policies in the upgrade plan.
212 3. It is required to execute properly on various configurations of
213    system object. I.e. stand-alone, HA, etc.
214 4. It is required to execute on the designated different parts of the
215    system. I.e. physical server, virtualized server, rack, chassis,
216    cluster, even different geographical places.
217
218 Testing (online)
219 ^^^^^^^^^^^^^^^^
220
221 The testing after upgrade the whole system or parts of system to make
222 sure the upgraded system(object) is working normally.
223
224 .. <hujie> Revised text to be general.
225
226 1. It is recommended to run the prepared test cases to see if the
227    functionalities are available without any problem.
228 2. It is recommended to check the sysinfo, e.g. system alarms,
229    performance statistics and diagnostic logs to see if there are any
230    abnormal.
231
232 Restore/Roll-back (online)
233 ^^^^^^^^^^^^^^^^^^^^^^^^^^
234
235 When upgrade is failure unfortunately, a quick system restore or system
236 roll-back should be taken to recovery the system and the services.
237
238 .. <hujie> Revised text to be general.
239
240 1. It is recommend to support system restore from backup when upgrade
241    was failed.
242 2. It is recommend to support graceful roll-back with reverse order
243    steps if possible.
244
245 Monitoring (online)
246 ^^^^^^^^^^^^^^^^^^^
247
248 Escalator should continually monitor the process of upgrade. It is
249 keeping update status of each module, each node, each cluster into a
250 status table during upgrade.
251
252 .. <hujie> Revised text to be general.
253
254 1. It is required to collect the status of every objects being upgraded
255    and sending abnormal alarms during the upgrade.
256 2. It is recommend to reuse the existing monitoring system, like alarm.
257 3. It is recommend to support pro-actively query.
258 4. It is recommend to support passively wait for notification.
259
260 **Two possible ways for monitoring:**
261
262 **Pro-Actively Query** requires NFVI/VIM provides proper API or CLI
263 interface. If Escalator serves as a service, it should pass on these
264 interfaces.
265
266 **Passively Wait for Notification** requires Escalator provides
267 callback interface, which could be used by NFVI/VIM systems or upgrade
268 agent to send back notification.
269
270 .. <hujie> I am not sure why not to subscribe the notification.
271
272 Logging (online)
273 ^^^^^^^^^^^^^^^^
274
275 Record the information generated by escalator into log files. The log
276 file is used for manual diagnostic of exceptions.
277
278 1. It is required to support logging.
279 2. It is recommended to include time stamp, object id, action name,
280    error code, etc.
281
282 Administrative Control (online)
283 ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^
284
285 Administrative Control is used for control the privilege to start any
286 escalator's actions for avoiding unauthorized operations.
287
288 #. It is required to support administrative control mechanism
289 #. It is recommend to reuse the system's own secure system.
290 #. It is required to avoid conflicts when the system's own secure system
291    being upgraded.
292
293 Requirements on Object being upgraded
294 =====================================
295
296 .. <hujie> We can develop BPs in future from requirements of this section and
297   gap analysis for upper stream projects
298
299 Escalator focus on smooth upgrade. In practical implementation, it
300 might be combined with installer/deplorer, or act as an independent
301 tool/service. In either way, it requires targeting systems(NFVI and
302 VIM) are developed/deployed in a way that Escalator could perform
303 upgrade on them.
304
305 On NFVI system, live-migration is likely used to maintain availability
306 because OPNFV would like to make HA transparent from end user. This
307 requires VIM system being able to put compute node into maintenance mode
308 and then isolated from normal service. Otherwise, new NFVI instances
309 might risk at being schedule into the upgrading node.
310
311 On VIM system, availability is likely achieved by redundancy. This
312 impose less requirements on system/services being upgrade (see PVA
313 comments in early version). However, there should be a way to put the
314 target system into standby mode. Because starting upgrade on the
315 master node in a cluster is likely a bad idea.
316
317 .. <hujie>Revised text to be general.
318
319 1. It is required for NFVI/VIM to support **service handover** mechanism
320    that minimize interruption to 0.001%(i.e. 99.999% service
321    availability). Possible implementations are live-migration, redundant
322    deployment, etc, (Note: for VIM, interruption could be less
323    restrictive)
324
325 2. It is required for NFVI/VIM to restore the early version in a efficient
326    way, such as **snapshot**.
327
328 3. It is required for NFVI/VIM to **migration data** efficiently between
329    base and upgraded system.
330
331 4. It is recommend for NFV/VIM's interface to support upgrade
332    orchestration, e.g. reading/setting system state.
333
334 Functional Requirements
335 =======================
336
337 Availability mechanism, etc.
338