4 Detailed architecture and message flows
5 =======================================
6
7 Within the Promise project we consider two different architectural options, i.e.
8 a *shim-layer* based architecture and an architecture targeting at full
9 OpenStack *integration*.
10
11 Shim-layer architecture
12 -----------------------
13
14 The *shim-layer architecture* is using a layer on top of OpenStack to provide
15 the capacity management, resource reservation, and resource allocation features.
16
17
18 Detailed Message Flows
19 ^^^^^^^^^^^^^^^^^^^^^^
20
21 Note, that only selected parameters for the messages are shown. Refer to
22 :ref:`northbound_API` and Annex :ref:`yang_schema` for a full set of message
23 parameters.
24
25 Resource Capacity Management
26 """"""""""""""""""""""""""""
27
28 .. figure:: images/figure5_new.png
29     :name: figure5
30     :width: 90%
31
32     Capacity Management Scenario
33
34 :numref:`figure5` shows a detailed message flow between the consumers and the
35 capacity management functional blocks inside the shim-layer. It has the
36 following steps:
37
38     * Step 1a: The Consumer sends a *query-capacity* request to Promise
39       using some filter like time-windows or resource type. The capacity is
40       looked up in the shim-layer capacity map.
41
42     * Step 1b: The shim-layer will respond with information about the
43       total, available, reserved, and used (allocated) capacities matching the
44       filter.
45
46     * Step 2a: The Consumer can send *increase/decrease-capacity* requests
47       to update the capacity available to the reservation system. It can be
48       100% of available capacity in the given provider/source or only a subset,
49       i.e., it can allow for leaving some "buffer" in the actual NFVI to be
50       used outside the Promise shim-layer or for a different reservation
51       service instance. It can also be used to inform the reservation system
52       that from a certain time in the future, additional resources can be
53       reserved (e.g. due to a planned upgrade of the capacity), or the
54       available capacity will be reduced (e.g. due to a planned downtime of
55       some of the resources).
56
57     * Step 2b: The shim-layer will respond with an ACK/NACK message.
58
59     * Step 3a: Consumers can subscribe for capacity-change events using a
60       filter.
61
62     * Step 3b: Each successful subscription is responded with a
63       subscription_id.
64
65     * Step 4: The shim-layer monitors the capacity information for the
66       various types of resources by periodically querying the various
67       Controllers (e.g. Nova, Neutron, Cinder) or by creating event alarms in
68       the VIM (e.g. with Ceilometer for OpenStack) and updates capacity
69       information in its capacity map.
70
71     * Step 5: Capacity changes are notified to the Consumer.
72
73 Resource Reservation
74 """"""""""""""""""""
75
76 .. figure:: images/figure6_new.png
77     :name: figure6
78     :width: 90%
79
80     Resource Reservation for Future Use Scenario
81
82 :numref:`figure6` shows a detailed message flow between the Consumer and the
83 resource reservation functional blocks inside the shim-layer. It has the
84 following steps:
85
86     * Step 1a: The Consumer creates a resource reservation request for
87       future use by setting a start and end time for the reservation as well as
88       more detailed information about the resources to be reserved. The Promise
89       shim-layer will check the free capacity in the given time window and in
90       case sufficient capacity exists to meet the reservation request, will
91       mark those resources "reserved" in its reservation map.
92
93     * Step 1b: If the reservation was successful, a reservation_id and
94       status of the reservation will be returned to the Consumer. In case the
95       reservation cannot be met, the shim-layer may return information about
96       the maximum capacity that could be reserved during the requested time
97       window and/or a potential time window where the requested (amount of)
98       resources would be available.
99
100     * Step 2a: Reservations can be updated using an *update-reservation*,
101       providing the reservation_id and the new reservation_data. Promise
102       Reservation Manageer will check the feasibility to update the reservation
103       as requested.
104
105     * Step 2b: If the reservation was updated successfully, a
106       reservation_id and status of the reservation will be returned to the
107       Consumer. Otherwise, an appropriate error message will be returned.
108
109     * Step 3a: A *cancel-reservation* request can be used to withdraw an
110       existing reservation. Promise will update the reservation map by removing
111       the reservation as well as the capacity map by adding the freed capacity.
112
113     * Step 3b: The response message confirms the cancelation.
114
115     * Step 4a: Consumers can also issue *query-reservation* requests to
116       receive a list of reservation. An input filter can be used to narrow down
117       the query, e.g., only provide reservations in a given time window.
118       Promise will query its reservation map to identify reservations matching
119       the input filter.
120
121     * Step 4b: The response message contains information about all
122       reservations matching the input filter. It also provides information
123       about the utilization in the requested time window.
124
125     * Step 5a: Consumers can subscribe for reservation-change events using
126       a filter.
127
128     * Step 5b: Each successful subscription is responded with a
129       subscription_id.
130
131     * Step 6a: Promise synchronizes the available and used capacity with
132       the underlying VIM.
133
134     * Step 6b: In certain cases, e.g., due a failure in the underlying
135       hardware, some reservations cannot be kept up anymore and have to be
136       updated or canceled. The shim-layer will identify affected reservations
137       among its reservation records.
138
139     * Step 7: Subscribed Consumers will be informed about the updated
140       reservations. The notification contains the updated reservation_data and
141       new status of the reservation. It is then up to the Consumer to take
142       appropriate actions in order to ensure high priority reservations are
143       favored over lower priority reservations.
144
145 Resource Allocation
146 """""""""""""""""""
147
148 .. figure:: images/figure7_new.png
149     :name: figure7
150     :width: 90%
151
152     Resource Allocation
153
154 :numref:`figure7` shows a detailed message flow between the Consumer, the
155 functional blocks inside the shim-layer, and the VIM. It has the following
156 steps:
157
158     * Step 1a: The Consumer sends a *create-instance* request providing
159       information about the resources to be reserved, i.e., provider_id
160       (optional in case of only one provider), name of the instance, the
161       requested flavour and image, etc. If the allocation is against an
162       existing reservation, the reservation_id has to be provided.
163
164     * Step 1b: If a reservation_id was provided, Promise checks if a
165       reservation with that ID exists, the reservation start time has arrived
166       (i.e. the reservation is active), and the required capacity for the
167       requested flavor is within the available capacity of the reservation. If
168       those conditions are met, Promise creates a record for the allocation
169       (VMState="INITIALIZED") and update its databases. If no reservation_id
170       was provided in the allocation request, Promise checks whether the
171       required capacity to meet the request can be provided from the available,
172       non-reserved capacity. If yes, Promise creates a record for the
173       allocation and update its databases. In any other case, Promise rejects
174       the *create-instance* request.
175
176     * Step 2: In the case the *create-instance* request was rejected,
177       Promise responds with a "status=rejected" providing the reason of the
178       rejection. This will help the Consumer to take appropriate actions, e.g.,
179       send an updated *create-instance* request. The allocation work flow will
180       terminate at this step and the below steps are not executed.
181
182     * Step 3a: If the *create-instance* request was accepted and a related
183       allocation record has been created, the shim-layer issues a
184       *createServer* request to the VIM Controller providing all information to
185       create the server instance.
186
187     * Step 3b: The VIM Controller sends an immediate reply with an
188       instance_id and starts the VIM-internal allocation process.
189
190     * Step 4: The Consumer gets an immediate response message with
191       allocation status "in progress" and the assigned instance_id.
192
193     * Step 5a+b: The consumer subscribes to receive notifications about
194       allocation events related to the requested instance. Promise responds
195       with an acknowledgment including a subscribe_id.
196
197     * Step 6: In parallel to the previous step, Promise shim-layer creates
198       an alarm in Aodh to receive notifications about all changes to the
199       VMState for instance_id.
200
201     * Step 7a: The VIM Controller notifies all instance related events to
202       Ceilometer. After the allocation has been completed or failed, it sends
203       an event to Ceilometer. This triggers the OpenStack alarming service Aodh
204       to notify the new VMState (e.g. ACTIVE and ERROR) to the shim-layer that
205       updates its internal allocation records.
206
207     * Step 7b: Promise sends a notification message to the subscribed
208       Consumer with information on the allocated resources including their new
209       VMState.
210
211     * Step 8a+b: Allocated instances can be terminated by the Consumer by
212       sending a *destroy-instance* request to the shim-layer. Promise responds
213       with an acknowledgment and the new status "DELETING" for the instance.
214
215     * Step 9a: Promise sends a *deleteServer* request for the instance_id
216       to the VIM Controller.
217
218     * Step 10a: After the instance has been deleted, an event alarm is
219       sent to the shim-layer that updates its internal allocation records and
220       capacity utilization.
221
222     * Step 10b: The shim-layer also notifies the subscribed Consumer about
223       the successfully destroyed instance.
224
225
226 Internal operations
227 ^^^^^^^^^^^^^^^^^^^
228
229 .. note:: This section is to be updated
230
231 In the following, the internal logic and operations of the shim-layer will be
232 explained in more detail, e.g. the "check request" (step 1b in
233 :numref:`figure7` of the allocation work flow).
234
235
236
237 Integrated architecture
238 -----------------------
239
240 The *integrated architecture* aims at full integration with OpenStack.
241 This means that it is planned to use the already existing OpenStack APIs
242 extended with the reservation capabilities.
243
244 The advantage of this approach is that we don't need to re-model the
245 complex resource structure we have for the virtual machines and the
246 corresponding infrastructure.
247
248 The atomic item is the virtual machine with the minimum set of resources
249 it requires to be able to start it up. It is important to state that
250 resource reservation is handled on VM instance level as opposed to standalone
251 resources like CPU, memory and so forth. As the placement is an important
252 aspect in order to be able to use the reserved resources it provides the
253 constraint to handle resources in groups.
254
255 The placement constraint also makes it impossible to use a quota management
256 system to solve the base use case described earlier in this document.
257
258 OpenStack had a project called Blazar, which was created in order to provide
259 resource reservation functionality in cloud environments. It uses the Shelve
260 API of Nova, which provides a sub-optimal solution. Due to the fact that this
261 feature blocks the reserved resources this solution cannot be considered to
262 be final. Further work is needed to reach a more optimal stage, where the
263 Nova scheduler is intended to be used to schedule the resources for future
264 use to make the reservations.
265
266 Phases of the work
267 ^^^^^^^^^^^^^^^^^^
268
269 The work has two main stages to reach the final solution. The following main work items
270 are on the roadmap for this approach:
271
272 #. Sub-optimal solution by using the shelve API of Nova through the Blazar project:
273
274    * Fix the code base of the Blazar project:
275
276      Due to integration difficulties the Blazar project got suspended. Since the last
277      activities in that repository the OpenStack code base and environment changed
278      significantly, which means that the project's code base needs to be updated to the
279      latest standards and has to be able to interact with the latest version of the
280      other OpenStack services.
281
282    * Update the Blazar API:
283
284      The REST API needs to be extended to contain the attributes for the reservation
285      defined in this document. This activity shall include testing towards the new API.
286
287 #. Use Nova scheduler to avoid blocking the reserved resources:
288
289    * Analyze the Nova scheduler:
290
291      The status and the possible interface between the resource reservation system and
292      the Nova scheduler needs to be identified. It is crucial to achieve a much more
293      optimal solution than what the current version of Blazar can provide. The goal is
294      to be able to use the reserved resources before the reservation starts. In order to
295      be able to achieve this we need the scheduler to do scheduling for the future
296      considering the reservation intervals that are specified in the request.
297
298    * Define a new design based on the analysis and start the work on it:
299
300      The design for the more optimal solution can be defined only after analyzing the
301      structure and capabilities of the Nova scheduler.
302
303    * This phase can be started in parallel with the previous one.
304
305 Detailed Message Flows
306 ^^^^^^^^^^^^^^^^^^^^^^
307
308 .. note:: to be done
309
310 Resource Reservation
311 """"""""""""""""""""